Jupiter Animal Hospital Phase 1 Complete

7/29/2014

We did it. 14 hrs before opening, phase one completed. 2400 sq ft remodel in 8 days and 7 nights. Good job everyone!

Removed over 2000 sq ft of tile, demoed 2 baths and emptied entire hospital into storage.